2015 Environmental Management Plan

Offshore Pipeline Span Rectification Works

Rock Placement for Span Rectification Works Method Statement  

Environ review of Method Statement

01.09.2015 DCENR Letter of Agreement to SEPIL 

Water Outfall Pipeline Detachment Incident Investigation Report

Environmental Incident Notification Form No. 20

Water Outfall Pipeline Detachment – Incident Investigation Report

Environ review of Incident Investigation Report

19.08.015 DCENR Letter to SEPIL re Water Outfall Pipeline Detachment Incident Report

EMP Method Statement - Water Outfall Line Protection and Remedial Works Addendum - Nearshore Permanent Protection Works - Phase 3

Method Statement - Water Outfall Line Protection and Remedial Works Addendum - Nearshore Permanent Protection Works

Environ Review

Letter of Agreement 9th July 2015

 

EMP Method Statement – Water Outfall Line Protection and Remedial Works - Phase 2

Method Statement - Water Outfall Line Protection and Remedial Works - Phase 2

Environ Review

Letter of Agreement 4th June 2015

 

EMP Method Statement – Water Outfall Line Protection and Remedial Works - Phase 1

Method Statement - Water Outfall Line Protection and Remedial Works

Environ review of Water Outfall Line Protection and Remedial Works Method Statement

15.04.2015 Department's Letter of Agreement - Water Outfall Line Protection and Remedial Works

15.04.2015 Letter of Approval to conduct acoustic and visual survey inspection of Corrib Offshore Pipeline Water Outfall Line

Incident Reports

Environmental Incident Notification No 19_10 04 15

 

Discharge of fluid during rock placement activity

Notification from SEPIL re discharge of fluid during rock placement activity

DCENR to Environ Consultants re oil spill incident

Environmental incident Report no 21

Response from Environ Consultants advising that incident be closed off 

 

Subsea Construction Works 2015

Subsea Construction Works 2015 EMP

Environ Review of Subsea Construction Works 2015 EMP

22.06.2015 DCENR Letter of Agreement to SEPIL

24.07.2015 PUDAC Letter of Approval to SEPIL

 

MEG Displacement from the Produced Water Umbilical Core

MEG Displacement from the Produced Water Umbilical Core Method Statement

Environ Review of Method Statement

26.03.2015 DCENR Letter of Agreement to SEPIL

06.05.2015 PUDAC Letter of Approval to SEPIL

 

Aughoose Compound Reinstatement

Aughoose Compound Reinstatement Method Statement

Aughoose Reinstatement Works Noise Emissions Report

Environ Review of Aughoose Compound Reinstatement Method Statement

21.01.2015 DCENR Letter of Agreement to SEPIL